Motusmec / SHM requirement
Regulatory guide

Structural health monitoring requirement for tall buildings

Under TBDY 2018, real-time monitoring of earthquake and wind response became mandatory for buildings taller than 105 m. Here is who it covers, what AFAD's directive requires and when the system should be planned.

The Turkish Building Earthquake Code (TBDY 2018) came into force on 1 January 2019 and introduced special rules for tall buildings. One of them is the installation of a structural health monitoring (SHM) system in certain tall buildings: the building's response to earthquakes and wind is measured continuously with accelerometers, and the data is transmitted to AFAD, Türkiye's Disaster and Emergency Management Authority, in real time.

In short

Which buildings are covered?

The requirement applies to buildings that fall under the TBDY 2018 definition of tall buildings, are in Earthquake Design Class 1 or 2 and are taller than 105 metres. The Earthquake Design Class depends on the seismic hazard at the site and the building's occupancy class; buildings in high-hazard regions fall into these classes. The safest way to check is the DTS value in the project's design reports.

What does the directive require?

AFAD's directive requires accelerometer data to be transferred simultaneously to the Structural Health Monitoring Centre (YSİM) within AFAD, so that damage threatening safety can be detected quickly after an earthquake from the building's dynamic properties. Key technical requirements include:

Source: AFAD, Structural Health Monitoring System Implementation Directive (09.01.2020), articles 1–6.

When should the system be planned?

The cleanest and most economical approach is to plan the sensor layout during design and structural construction, when cable routes, the recorder room and power lines can easily be built into shafts and slabs. Retrofitting a completed building can disturb finishes, lengthen cable runs and raise costs.

Beyond compliance: what is the data for?

The directive requires the data to be collected and sent to AFAD; the real value lies in interpreting it. With a well-designed system you get:

Post-earthquake decisionsIs the building safe? Is it usable? Evacuation and re-occupancy decisions rest on measurement.
Wind and comfortSway on upper floors and damper performance are tracked.
Long-term trendsChanges in modal frequencies are followed over years and inform maintenance decisions.

What Motusmec does

Motusmec is a structural and earthquake engineering firm at Boğaziçi University Technopark, Istanbul. For tall buildings we provide:

  1. Sensor layout design and a system that meets the directive,
  2. Installation and commissioning, including data transfer to AFAD,
  3. 24/7 monitoring with our in-house software, developed with TÜBİTAK-TEYDEB support: dynamic identification, post-earthquake condition assessment and fatigue life estimation,
  4. Long-term performance reports and automatic event-driven reports.

Our team published long-term monitoring experience from three instrumented tall buildings in Istanbul, including measurements before, during and after an Mw 5.7 earthquake, in the Bulletin of Earthquake Engineering. The AFAD-funded research project on a structural health monitoring standard for tall buildings (UDAP-G-17-01) was carried out at Boğaziçi University.

Frequently asked questions

Is monitoring mandatory for buildings under 105 m?

The TBDY 2018 requirement applies to buildings taller than 105 m in Earthquake Design Class 1 and 2. It is not mandatory for lower buildings, but it is increasingly installed voluntarily in hospitals, data centres, base-isolated buildings and critical public buildings so that decisions can be made quickly after an earthquake.

Who is responsible for installation and maintenance?

Under AFAD's directive, the building owner who obtains the occupancy permit must arrange and pay for the installation and maintenance of the accelerometers and is accountable to AFAD.

Where does the data go?

Accelerometer data is transferred in real time to the Structural Health Monitoring Centre (YSİM) within AFAD and is processed under Türkiye's Personal Data Protection Law No. 6698.

Can a system be retrofitted to an existing tall building?

Yes. In a retrofit, sensor locations, cable routes and the recorder location are planned around the existing architecture. For new projects, the best time is the structural construction phase.

What if a system is installed but nobody interprets the data?

The directive's minimum requirement is to collect and transmit the data. Deciding whether a building is safe and usable after an earthquake requires regular analysis; Motusmec can connect to existing systems and take over analysis and reporting.

Let's monitor your structure.

Tell us about your project stage and structure type, and we will map out sensor layout, installation and monitoring for you.

info@motusmec.com.tr